Commercial fit-out rescue
- Property
- Industrial / commercial unit with mezzanine
- Location
- Warwickshire
- Timescale
- Multi-week programme delivered to client's reopening date
The problem
The previous contractor had walked off site leaving multiple trades unfinished — electrical incomplete, no fire alarm system, structural cavity wall ties missing, no external path, and the staff toilet block half-built.
Scope of works
- Full electrical fit-out across the unit
- Complete fire alarm system installation
- Structural cavity wall tie installation
- Wrap-around external commercial path
- Small block of staff / commercial toilets — built and finished
- Snagging and rectification of all previous contractor's incomplete work
Trades involved
Outcome
Site rescued, every outstanding trade closed out, the toilet block fully built and the unit handed over ready for occupation and operation.